The seven basic quality tools are used within in the context of the PDCA Cycle to solve quality-related problems.These tools are used in()in the following processes.(2017年下半年系统集成项目管理工程师)

The seven basic quality tools are used within in the context of the PDCA Cycle to solve quality-related problems.These tools are used in()in the following processes.(2017年下半年统集成项目管理工程师)
A、plan quality management
B、perform quality assurance
C、perform quality control
D、perform quality improvement






参考答案:C