()is the process of implementing risk response plans,tracking identified risks,monitoring residual risk,identifying new risk,and evaluating risk process effectiveness throughout the project.(2017年下半年系

()is the process of implementing risk response plans,tracking identified risks,monitoring residual risk,identifying new risk,and evaluating risk process effectiveness throughout the project.(2017年下半系统集成项目管理工程师)
A、Identity risks
B、Control risks
C、Plan risk responses
D、Plan risk management






参考答案:B