( )is the process of obtaining the stakeholders' formal acceptance of the completed project scope. Verifying the scope includes reviewing deliverables and work results to ensure that all were complete
( )is the process of obtaining the stakeholders' formal acceptance of the completed project scope. Verifying the scope i...
-
( )are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion; they may also exert influence
( )are individuals and organizations that are actively involved in the project, or whose interests may be affected as a...
-
( )is a measurable, verifiable work product such as a specification, feasibility study report, detail design document, or working prototype.(2005年上半年信息系统项目管理师真题解析)
( )is a measurable, verifiable work product such as a specification, feasibility study report, detail design document, o...
-
The( )technique involves using project characteristics in a mathematical model to predict total project costs. Models can be simple or complex. (2005年上半年信息系统项目管理师真题解析)
The( )technique involves using project characteristics in a mathematical model to predict total project costs. Models ca...
-
The( )describes the business need, justification, requirements, and current boundaries for the project. It provides important information about project requirements that is considered during cost est
The( )describes the business need, justification, requirements, and current boundaries for the project. It provides impo...
-
For example, in most application areas, additional work during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. The cost estimat
For example, in most application areas, additional work during a design phase is widely held to have the potential for r...
-
Estimating schedule activity costs involves developing an( )of the costs of the resources needed to complete each schedule activity. Cost estimating includes identifying and considering various costin
Estimating schedule activity costs involves developing an( )of the costs of the resources needed to complete each schedu...
-
( )the initiation of the successor activity, depends upon the initiation of the predecessor activity. (2005年上半年信息系统项目管理师真题解析)
( )the initiation of the successor activity, depends upon the initiation of the predecessor activity. (2005年上半年信息系统项目管理...
-
This method includes following types of dependcies orprecedence relationships: ( )the initiation of the successor activity, depends upon the completion of the predecessor activity. (2005年上半年信息系统项目管理师
This method includes following types of dependcies orprecedence relationships: ( )the initiation of the successor activ...
-
( ) is a method of constructing a project schedule network diagram that uses boxes or rectangles,referred to as nodes,to represent activites and connects them with arrows that asow the dependencies.(
( ) is a method of constructing a project schedule network diagram that uses boxes or rectangles,referred to as nodes,t...
-
关于 kerberos 和 PKI 两种认证协议的叙述中正确的是( ),在使用 kerberos 认证 时,首先向密钥分发中心发送初始票据( )来请求会话票据,以便获取服务器提供的服务。(2005年上半年信息系统项目管理师真题解析)
关于 kerberos 和 PKI 两种认证协议的叙述中正确的是( ),在使用 kerberos 认证 时,首先向密钥分发中心发送初始票据( )来请求会话票据,以便获取服务器提供的服务。(2005年上半年信息系统项目管理师真题解析) A...
-
在距离矢量路由协议中,防止路由循环的技术是( )。(2005年上半年信息系统项目管理师真题解析)
在距离矢量路由协议中,防止路由循环的技术是( )。(2005年上半年信息系统项目管理师真题解析) A、使用生成树协议删除回路 B、使用链路状态公告(LSA)发布网络的拓扑结构 C、利用水平分裂法阻止转发路由信息 D、利用最短通路优先算法计算...
-
划分虚拟局域网(VLAN )有多种方式,以下划分方式中,不正确的是( )。(2005年上半年信息系统项目管理师真题解析)
划分虚拟局域网(VLAN )有多种方式,以下划分方式中,不正确的是( )。(2005年上半年信息系统项目管理师真题解析) A、基于交换机端口划分 B、基于网卡地址划分 C、基于用户名划分 D、基于网络层地址划分 参考答案:C 参考解析:...
-
用路由器把一个网络分段,这样做的好处是( )。(2005年上半年信息系统项目管理师真题解析)
用路由器把一个网络分段,这样做的好处是( )。(2005年上半年信息系统项目管理师真题解析) A、网络中不再有广播通信,所有的数据都通过路由器转发 B、路由器比交换机更有效率 C、路由器可以对分组进行过滤 D、路由器可以减少传输延迟 参考...
-
当以下条件同时满足时,监理方应受理( )提出的费用索赔申请。1)索赔事件造成了承包单位直接经济损失;2) 索赔事件是由于非承包单位的责任发生的;3) 承包单位已按照施工合同规定的期限和程序提出费用索赔申请表,并附有索赔凭证 材料。(2005年上半年信息系统项目管理师真题解析)
当以下条件同时满足时,监理方应受理( )提出的费用索赔申请。1)索赔事件造成了承包单位直接经济损失;2) 索赔事件是由于非承包单位的责任发生的;3) 承包单位已按照施工合同规定的期限和程序提出费用索赔申请表,并附有索赔凭证 材料。(2005...