Estimating schedule activity costs involves developing an( )of the costs of the resources needed to complete each schedule activity. Cost estimating includes identifying and considering various costin
* 注意事项
本文仅代表作者观点,不代表本站立场。
本文系作者授权发表,转载需标明出处。
软考题网站(https://www.ruankaoti.com/)提供的相关试题资料仅供个人复习参考使用
如果您有更好的解答,欢迎留言评论。
- 上一篇: ( )the initiation of the successor activity, depends upon the initiation of the predecessor activity. (2005年上半年信息系统项目管理师真题解析)
- 下一篇: For example, in most application areas, additional work during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. The cost estimat
发表评论